沈阳某商业中心电梯工程施工组织设计电梯、扶梯安装施工方案
××××电梯有限公司沈阳分公司
一、方案编制依据............................................1
二、工程概况及施工条件
DB37/T 5143-2019 城市道路工程现场文明施工管理标准1.主体工程概况.................................................2
2.电梯工程概况.................................................2
3.施工条件.....................................................6
1.施工人员及组织机构............................................6
2.电梯、扶梯施工时间安排........................................7
3.施工前各项准备................................................9
1.垂直提升电梯安装施工方法.....................................10
1.1样板架安装、挂基准线....................................10
1.2导轨架及导轨安装........................................14
1.3机房机械设备安装........................................16
1.4对重安装................................................19
1.5轿厢安装................................................21
1.6层门安装................................................26
1.7井道机械设备安装........................................28
1.8钢丝绳安装..............................................31
1.9电气装置安装............................................34
1.10整机调试................................................41
2.扶梯、自动人行道安装施工方法................................49
2.1施工工艺流程图..........................................49
2.2准备工作................................................50
2.3基础放线................................................51
2.4水平运输................................................52
2.5桁架吊装................................................53
2.6安全保护装置的安装......................................55
2.7梯级与梳齿板安装........................................57
2.8围板安装................................................59
2.9扶手带的安装与调整......................................60
2.10电气装置安装与调整.....................................61
2.11运行试验...............................................63
1.质量保证体系及工作流程.......................................64
2.施工质量标准.................................................65
1.一般规定....................................................65
2.井道内施工安全措施................................................65
3.现场搬运安全措施..................................................65
4.设备使用安全措施..................................................65
5.设备吊装安全措施..................................................66
6.机械部件安装安全措施.............................................66
7.电气设备安装安全措施.............................................66
8.调试施工安全措施..................................................66
七、环境保护措施..................................................66
八、应急预案........................................................67
1、中华人民共和国安全生产法(中华人民共和国主席令第70号令)
17、自动扶梯梯级链、附件及滚轮JB/T8545—1997
18、《电梯与自动扶梯技术规范》学苑出版社
二、工程概况及施工条件
沈阳××××××××工程
××××××设计研究院有限公司
××××××事务所、××××××有限公司
沈阳××××××××××
××××××电梯有限公司在某项目一期电梯、扶梯设备供应、安装项目中标,担负了全部垂直提升电梯、自动扶梯、自动人行道的设备供应和设备安装工作。
本项目共安装垂直提升电梯36部CECS 508-2018-T标准下载,其中裙楼安装22部,塔楼安装14部;安装自动扶梯、自动人行道共75部,分别安装在裙楼地下三层至六层等不同部位。
根据业主要求,直梯安装计划分三个阶段进行,第一阶段安装电梯10部,工期60天;第二阶段安装电梯12部,工期90天;第三阶段安装电梯14部,工期90天。
自动扶梯、自动人行道施工计划分两个阶段进行,第一个阶段为扶梯进场并吊装到位,工期60天。第二个阶段为扶梯安装和试运行,工期为60天。
GY/T 5084-2011 广播电视工程工艺接地技术规范全部垂直电梯及扶梯、自动人行道规格、型号参数等详细情况见下表:
35层/35站36层/36站
12a、12b、12c