施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
五层框架综合教学楼工程量计算及施工组织设计S=(68.04+4)*(21.24+4)=1818.290m2
单桩:(12+0.6+0.2)*1/4*3.14*0.8²=6.431m3
共计:1.3*48*6.431=401.294m3
1)混凝土工程量:V=3.14D²HN/4=0.7854*0.8*0.8*12.8.*8=51.47m3
某污水处理段村污水提升泵站日提升5000吨及管网建设施工组织设计.doca.主筋:G=12.8*12*0.888*8*1.02=1113.00Kg
b.箍筋:G=8.076*12.8*8*1.02=843.52Kg
c.钢筋小计:1113.00+843.52=1956.52Kg
1)混凝土工程量:V=3.14D²HN/4=0.7854*0.9*0.9*12.8.*4=32.57m3
a.主筋:G=12.8*12*0.888*4*1.02=556.50Kg
b.箍筋:G=8.076*12.8*4*1.02=421.76Kg
c.钢筋小计:556.50+421.76=978.26Kg
1)混凝土工程量:V=3.14D2HN/4=0.7854*0.8*0.8*12.8.*20=128.68m3
a.主筋:G=12.8*12.13*0.888*20*1.02=3014.37Kg
b.箍筋:G=8.076*12.8*20*1.02=2108.81Kg
c.钢筋小计:3014.37+2108.81=5123.18Kg
1)混凝土工程量:V=3.14D2HN/4=0.7854*0.8*0.8*12.8.*16=102.94m3
a.主筋:G=12.8*13*0.888*16*1.02=2411.50Kg
b.箍筋:G=8.076*12.8*16*1.02=1087.04Kg
c.钢筋小计:2411.50+1087.04=3498.54Kg
模板:S=(2.1+3.0)*0.35*2*8+6.6*0.35*2*4+4.8*2*16*0.35+(3.0+2.1+1.5)*0.4*2*6+(3.0+2.1)*0.35*2*6+(3.3+2.4)*0.3*2*6+
4.5*0.4*2*6+3.9*0.35*2*5+3.6*0.5*2*2+3.0*0.5*2*2
G=[(3.0+2.1)*1.21*6*5.1*1.58*4]*8=554.06Kg
G=0.395*l*n*8=72.81Kg
c.钢筋小计:554.06+72.81=626.87Kg
G=[6.6*2.98*4+6.6*2.47*2+6.6*2.0*2+6.6*1.58*2]*4=634.13Kg
G=0.395*l*n*4=47.02Kg
c.钢筋小计:634.13+47.02=681.15Kg
G=[(3.0+2.1+1.5)*4*2.47+(3.0+2.1+1.5)*4*2.0+(3.0+2.1+1.5*2*1.58)]*6=833.18Kg
G=0.395*l*n*6=77.88Kg
c.钢筋小计:833.18+77.88=911.06Kg
G=(4.8*4*1.21+4.8*2*2.0+4.8*4*1.58)*16=1164.29Kg
G=0.395*l*n*16=109.21Kg
c.钢筋小计:1164.29+109.21=1273.50Kg
G=(3.0+2.1)*(2*2.0+2*1.21+2*1.58+4*1.58)*6=486.54Kg
G=0.395*l*n*6=65.98Kg
c.钢筋小计:486.54+65.98=552.52Kg
G=1.5*3*(3*2.0+5*1.58)*6=375.3Kg
G=0.395*l*n*6=54.75Kg
c.钢筋小计:375.3+54.75=430.05Kg
G=3.3*(8*1.21+4*1.58)*6=316.8Kg
G=0.395*l*n*6=38.73Kg
c.钢筋小计:316.8+38.73=355.53Kg
G=2.4*(8*1.21+4*1.58)*6=230.4Kg
G=0.395*l*n*16=38.73Kg
c.钢筋小计:230.4+38.73=269.13Kg
G=3.9*(6*1.21+4*1.58)*5=264.81Kg
G=0.395*l*n*5=34.13Kg
c.钢筋小计:264.81+34.13=298.94Kg
G=(3.0+3.6)*(6*2.98+2*3.85)*2=337.66Kg
G=0.395*l*n*2=40.81Kg
c.钢筋小计:337.66+40.81=378.47Kg
钢筋工程量总计:5736.411Kg
V=(2.1+3.0)*0.35*0.30*8+6.6*0.35*0.30*4+4.8*0.35*0.3*16+
(3.0+2.1+1.5)*0.4*0.3*6+(3.0+2.1)*0.35*0.3*6+(3.3+2.4)*0.3*0.3*6+(1.5+1.5+1.5)*0.4*0.3*6+3.9*0.35*0.3*5+
3.6*0.5*0.3*2+3.0*0.5*0.3*2=34.4m3
2.2底层柱、梁、楼板工程量计算
底层柱模板工程量总计:308.88m2
G=(52+42+25+19)*18+(52+39+85+66)*6+(24+18+151+93)*8+(113+96+291+598)*4+(87+112+79+67)*2+(107+143+89+47)*2
S=(0.4*2+0.25)*3.3*10+(0.45*2+0.25)*5.1*12+(0.3*2+0.25)*4.8*16+(0.35*2+0.25)*4.8*16+(0.45*2+0.25)*10.2*6+(0.4*2+0.25)*13.2*3+(0.3*2+0.25)*2.4*5+(0.3*2+0.25)*3.3*2
G=5.1*(4*2.0+2*1.58+2*1.21)*8=554.064Kg
G=0.395*l*n*8=69.84Kg
c.钢筋小计:554.064+69.84=623.904Kg
G=3.3*8*3.85*8=813.12Kg
G=0.395*l*n*8=54.61Kg
c.钢筋小计:813.12+54.61=867.73Kg
G=3.6*(4*2.47+1*2.0+2*3.85)8=563.904Kg
G=0.395*l*n*8=63.64Kg
c.钢筋小计:563.904+63.64=627.546Kg
G=3.0*8(6*2.98+2*2.47+4*3.85)*8=917.28Kg
G=0.395*l*n*8=43.482Kg
c.钢筋小计:917.28+43.482=960.762Kg
G=2.1*(2*1.21+2*1.58+2*0.888)*8=123.581Kg
G=0.398*l*n*8=40.50Kg
c.钢筋小计:123.581+40.50=164.082Kg
G=4.8*(5*1.58+1*1.21)*32=1399.296Kg
G=0.398*l*n*8=84.376Kg
c.钢筋小计:1399.296+84.376=1483.672Kg
G=3.3*(2*0.888+3*1.58+2*2.0)*8=277.622Kg
G=0.398*l*n*8=60.751Kg
c.钢筋小计:277.622+60.751=338.373Kg
G=2.4*(5*1.58+1*2.47)*10=248.88Kg
G=0.398*l*n*10=39.322Kg
c.钢筋小计:248.88+39.322=288.202Kg
G=2.1*(2*0.888+2*2.0+2*2.47)*6=135.022Kg
G=0.398*l*n*6=30.948Kg
c.钢筋小计:135.022+30.948=165.971Kg
G=5.1*(3*2.0+2*2.47)*6=334.764Kg
G=0.398*l*n*6=74.792Kg
c.钢筋小计:334.764+74.792=409.56Kg
G=4.5*(4*2.0+4*1.58)*6=386.64Kg
G=0.398*l*n*6=49.288Kg
c.钢筋小计:386.64+49.288=165.971Kg
钢筋总计:6365.73Kg
V=0.4*0.25*3.3*10+0.45*0.25*5.1*12+0.3*0.25*4.8*16+0.35*0.25*4.8*16+0.45*0.25*10.2*6+0.4*0.25*13.2*3+0.3*0.25*2.4*5
+0.3*0.25*3.3*2
2.2.3楼板:预应力空心板
S=6.6*(2.1+3.0+2.1+1.5+1.5)*2+4.8*(3.0+2.1+1.5)*8+3.3*(3.0+2.1+1.5*3)*2+2.4*(3.0+2.1+1.5*3)*2+4.8*(3.0+2.1+1.5*3)+3.0*3.9+3.6*(3.9+2.4+1.5)
2.3三层柱、梁、楼板工程量
G=(52+39+55+21)*18+(38+28+21+33)*6+(49+57+151+93)*8+(113+96+291+598)*4+(79+67+13+11)*2+(29+22+27+12)*2+(89+47+26+49)*2
S=[(0.35*2+0.25)*(2.1+3)*6+3.3*(0.25+0.3*2)*10+4.8*(0.25+0.35*2)*12+(2.1+1.5)*(0.25+0.45*2)*5+4.8*(0.25+0.3*2)*4+(1.5+1.5)*(0.25+0.45*2)*2+3.3*(0.25+0.45*2)*2]*2+(2.4+4.8+2.4)*(0.25+0.6*2)+(2.4+4.8+2.4)*(0.25+0.35*2)+(1.5+2.1)*(0.25+0.35*2)*2
某县中心渔港施工组织设计G=(3+2.1)*(4*2.47+2*1.58+1*1.21)*8=581.0Kg
G=0.398*l*n*8=74.0Kg
c.钢筋小计:581.0+74.0=655.0Kg
G=(3+2.1)*(4*2+4*2.98+1*2.47)*4=458.2Kg
G=0.398*l*n*4=46.0Kg
c.钢筋小计:458.2+46.0=504.2Kg
G=[3*(2*2.47+4*3.85+2*3.85+2*2.98)]*6=612.0Kg
LY/T 2014-2012标准下载G=0.398*l*n*6=32.90Kg