污水提升泵站压密注浆工程专项施工方案污水提升泵站压密注浆施工方案
污水提升泵站压密注浆主要针对其基坑底板下部的约1.8m厚的粉土,因其底板呈阶梯部,部份土体滑动,造成部份底板与其下部粉土的分离,而形成空洞,目前通过现场勘察,因破坏处为16×3×1.8m。因而要求采用注浆方式进行土体加固。Thisplanismainlyaimedatabout1.8mTHKpowdersoilinthebottomslaboffoundationpit.Asthebottomslabisinastepandpartofthesoilisslided,someslabsareseparatedfromthepowdersoil.Sothehollowsturnup.Afterthesiteinvestigation,asthebrokenareais16*3*1.8m,methodofgroutingshouldbeadoptedforthesoilstrengthening.
压密注浆方法MethodologyforCompactionandGrouting
塔冢村居民回迁楼项目(一期)-主楼施工组织设计施工淮备ConstructionPreparation
设置制浆站、加浆站尽量减少移动次数。Establishthemortarprocessstationandaddingstationtominimizethetimesofremoval.
备料、搭建水泥存放点。Materialpreparation.Andbuildthestorageforcement.
施工计划ConstructionPlan
施工设备:水泥浆压力泵一台;泥浆搅拌桶一台;储浆桶一只;注浆杆一根;注浆管50m。ConstructionEquipments:Onecementmortarpressurepump.Onebucketforcementmortarmixing.Onebucketforstorage.Onepoleformortarfillingand50mconduit.
施工技术要求ConstructionTechnicalRequirements
1、技术要求:TechnicalRequirements
因施工地块现已浇注混凝土底板,固采用风镐进行人工开孔,孔距为2.0m~1.5m,呈梅花形布孔,这样有利于浆液充填。Asthesitehasbeenplacedwithconcrete,holeswillbemadebymanpowerwithairpick.Theseholeswillbeinaplumblossomshape,withclearanceof2.0m~1.5mtofacilitatethefullfilling.
压浆设备采用200型高压泵注浆,机械动力采用自备柴油机动力,此泵最大压力可达到8MPa。200typeHPpumpandselfowneddieselgeneratorwillbeused.Themaximumpressureofpumpis8MPa.
注浆时应采取跳越注浆,这样可使浆液充填密实。Itwillbegroutedinskiptomeetthedensityrequirement.
工艺流程:WorkmanshipFlowChart
人工依尺寸成孔搅拌水泥浆液小压力注浆待初凝后再度注浆封孔。ManualHolesMakingAsSized
CementMortarMixingGroutingwithLPSecondGrouting(Afteritisgenerallyconsolidated.)SealHoles
注浆技术要求:TechnicalRequirementsforGrouting
水泥浆液配制水灰比0.5~0.6;初次注浆时压力控制在0.2~0.3之间;待12小时后,再次注浆,二次注浆压力不得超过0.5MPa。以防止压力过大,造成基坑底板的破坏,注浆时可依据现场施工情况下调整注浆压力。Thewatercementratiois0.5~0.6.Intheinitialgrouting,thepressureshouldbecontrolledwithin0.2~0.3.Itwillbesecondlygroutedafter12h.Thesecondtimepressurecannotexceed0.5MPatoavoidthedamageforbottomslab.Thepressurecanbeadjustedaccordingtotheactualcondition.
浆液配制采用425#普通硅酸盐水泥,水灰比0.5~0.6,注浆量以浆满出底板为止。425#Portlandcementwillbeusedformixing,withthewatercementratioof0.5~0.6.Theareamustbefilledtillthemortarexceedsthebottomslab.
注浆管采用高压注浆管DB37/T 4085-2020 商务楼宇安全隐患排查治理体系实施指南.pdf,接头处应保证可承受1.0MPa的压力。HPgroutingconduitshallbeused.Pressureintheendshouldbear1.0MPa.
注浆过程中应时刻观察现场情况,以便控制注浆量与注浆压力,以免对基础底板造成不必要的破坏。Intheperiodofgrouting,takecareofthesiteconditionforthequantityandpressurecontrol.
质量保证措施QualityAssuranceMeasures
建立以项目负责为主的质量管理体系,严格落实各工序质量责作任制。Establishthequalitymanagementsystemandcarryouttheresponsibilitysystemforeachprocedure.
认真观察现场施工情况GB50955-2013 石灰石矿山工程勘察技术规范.pdf,并做好现场施工记录。Carefullyinvestigatetheconstructionconditionandmakerecords.
安全措施SafetyMeasures
各工序、工种严格按相应的安全规定作业,严禁“三违施工”。Allcraftsandproceduresshouldstrictlyfollowsafetyrules.“ThreeDisobeyedConstructions”areforbidden.