天津某工业厂房施工组织设计(英文)CONSTRUCTIONORGANIZATIONDESIGN
FRAMEWORKSFOR
Description
Natureoftheworks:InvestorandowneroftheworksisBASFChemicalCo.,Ltd.andTECHNIPTIANCHENCHEMICALENGINEERING(TIANJIN)Co.,Ltd.isresponsibleforgeneralcontractmanagement.
深圳地铁5号线综合楼工程悬挑脚手架施工方案Basisoftheorganizationdesign:
Workingdrawings,designdescriptionandrelatedstandardatlasprovidedbyTECHNIPTIANCHENCHEMICALENGINEERING(TIANJIN)Co.,Ltd.;
Topographyoftheconstructionsiteandexistingbuildings(structures)ortobebuiltinthesurroundingsoftheworks;
Constructioncontractfortheworks;
Geologicalreport;
Nationalspecifications,procedures,standardsorcodesforacceptanceofworksandShanghaiMunicipalregulationsandrequirementsinrespectofbuildingconstructionbeingcurrentlyeffective.
Outlineoftheworks
Outlineoftheworks
SequenceNo.
Numberingofworks
Nameofunitworks
Buildingarea(m2)
Typeofstructure
THFequipment
Sitecondition
Constructionarrangement
Constructionorganizationmanagement
ProjectmethodswillbeconductedfortheconstructionandwewillestablishaProjectDepartmentinchargeofperformingthecontractinallrespects,organizing,inductingmanaging,coordinatingandcontrollingtheconstruction.TheprojectDept.willtakescientificmanagement,crackandhighlyeffectiveteamaswellasreasonablestructureasitsprincipletoformastrongconstructionteamfortheworks’construction,meanwhile,acceptthesupervisionsofownerandsupervisorssotoensurethetimeandqualityoftheconstruction.
3.1.2Stressonplanningmanagement,properlyworkoutmonth,weekanddayworkplans,setupareliablematerialsandsupportingsystemtotheextentthatthesupplycanbeensuredandthetransportationmeetsanyrequirement.
Safetyinspectionsection:Befamiliartosafetyoperationproceduresandlaborprotectionordinance,taketheresponsibilityforsafetyandcivilizationinspectionintheconstructionprocessandputforwardopinionsforrectification.
Materialssection:Shallbefamiliartotheperformanceandqualityrequirementsofthematerials,preparematerialsprocurementandsupplyplans,buycorrespondingconstructionmaterialsintimeperrequiredbytheworks,takegoodcareofthematerialssuchasstorage,positionedstackingetc,timelyprovidedocumentationinformationinrespectofthequalityofthematerialstotechnologySection.
Financial&budgetsection:properlytaketheresponsibilityforexaminingandcalculatingthecostfortheworks,statisticsofthequantityoftheworks,paymentcollection,alternationoftheconstructionbudgetetc.
Supportingsection:Shallberesponsibleforlivingandlogisticswork,sitesecurity,sitecleaningandmaintainingwork.
Variousoperationalgroupswillbesetupfororganizinglaborspertradefortheworkssuchascarpentergroup,steelbendergroup,scaffoldingworkgroup,concretegroup,masonrygroup,installationgroupetc.tooperateundercoordinationandunifieddirection.
3.1.5OrganizationofconstructionmanagementstaffsasFigure1hereunder:
Optionsformainconstructiontechnologies
Rebarworks:Fabricateandprocessrebarworksothesite,adoptbothflashingbuttweldandarcweldforthehorizontaljointsofrebar,mainlyhandlingthemwithmanpowerwithinthesite.Useelectroslagpressingweldforverticalrebarjoints.
Formwork:Splicedwithplywood(thickness:18)andsupporteditwith(48steelpipeforformwork.
Scaffoldingworks:Weusesteelpipescaffoldingofgroundtypeandwithcouplers.
Verticaltransportation:Wemainlyusederrickforthetransportationandprovideitwitha16tmobilecranewheninstallingroofrebar.
Constructionsequences:
Scheduleoffabricationoftestcubes(referencetotable2forthedetail):
Positionstobetested
Designedgrade
Bottomslabofpoolunderground
Wallslabsofpoolunderground
Structurestoryat100.00level
Equipmentfoundationabove100.00level
Pillarsfortechnicallevel
Beamslabsfortechnicallevel
ColumnsofLevel1
Beamslabsof111.000level
Beamslabsoflevel106.5
Equipmentfoundationabove111.00
Persontoacceptance
THFcushioncaps
Construction.Manager,SupervisorEngineer.
THFequipmentfoundation
Construction.Manager,SupervisorEngineer.
THFcushioncaps
Concreteoutlook
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Rebar,column
Construction.Manager,SupervisorEngineer.
Technicallevel
Rebar,beamslab
Construction.Manager,SupervisorEngineer.
111.00toplevel
Rebar,beamslab
Construction.Manager,SupervisorEngineer.
Construction.Manager,SupervisorEngineer.
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Concreteoutlook
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Construction.Manager,SupervisorEngineer.
100.00footinglevel
Rebar,column
Construction.Manager,SupervisorEngineer.
106.50Toplevel
Rebar,beamslab
Construction.Manager,SupervisorEngineer.
Doublecheck
Constructiongroups
Personinchargeofdoublecheck
Measurement&positioning
Surveygroup
Qualitymanager
Detailingdrawingforrebarworks
Steelbendergroup
Qualitymanager
Detailingdrawingfortimberworks
Carpentergroup
Qualitymanager
Earthworks,Excavation
Commongroup
Qualitymanager
Cuttingpipes
Masonrygroup
Qualitymanager
Formworkofbedding
Carpentergroup
Qualitymanager
Beddingconcrete
Concretergroup
Qualitymanager
Rebarforcushioncapandequipmentfoundation
Steelbendergroup
Qualitymanager
Formworksforcushionandequipmentfoundation
Carpentergroup
Qualitymanager
Concreteofcushionandequipmentfoundation
Concretergroup
Qualitymanager
Carpentergroup
Qualitymanager
Formworkfor100.00level
Carpentergroup
Qualitymanager
Rebarfor100.00level
Steelbendergroup
Qualitymanager
Concreteof100.00level
Concretergroup
Qualitymanager
Formworkfortechnicallevel
Carpentergroup
Qualitymanager
Formworkfortechnicallevel
Steelbendergroup
Qualitymanager
Rebaroftechnicallevel
Concretergroup
Qualitymanager
Formworkfor111.00level
Carpentergroup
Qualitymanager
Rebarof111.00level
Steelbendergroup
Qualitymanager
Concreteof111.00level
Concretergroup
Qualitymanager
Carpentergroup
Qualitymanager
Steelbendergroup
Qualitymanager
Concretergroup
Qualitymanager
QualityPlan
Technicalmanagement
Speciallyassignpersonstotakeresponsibilityforpreparingconstructionorganizationdesign,organizationdesignforsingleitemworksandnewtechnologicalcards,strictlycarryouttherulesinrespectofreview,approval.Alternationandinspectionbasedonthepracticeofconstructiontotheextentthattheworkscanbeexecutedonlyafterrelatedmethodsorplansmade.
Inadditiontopreparingconstructionorganizationandtechnologyscheme,organizestaffsandlaborstostudythemandproperlyconducttellingthetechnicaldetailsaswellastheworkingposttraining.
Organizetheworkofprocessing,orderinganddetailingdrawings,uniformlymanageprocessingandorderingmaterialsathomeandabroad,performthedoublecheckinrelationthereto.
Stressoninspection,testandhandlingworkofrawmaterials,factory’scertificate,permitandcertificatesofsitedoublecheck.
Stressontechnicalcontrolinspecialprocess.
Technicalprotectionmeasuresforfinishedproducts.
Qualitycontrol
Perfectlyestablishaqualitycontrolsystemtotheextentthatpostliabilitysystemcanbeputintopractice,thedutyassignedtoeachpersonandanexaminingsystemcanbeimplemented.
Establishaleadinggroupforgoodqualitycreatingactivities.
Focusonthequalityofpilefoundationtreatment,buttweldofrebar,concretepouringandthemainstructureworks.
Setupaqualitycontrolgroupforthequalitycontrolofspecialprocess,andproperlyconductqualitycontrolworksuchasplan,execution,inspection,conclusion,improvementetc.applyingPDCNcirculationprincipletotheextentthatenablethewholeprocessalwaysunderastablecontrol.
StrictlycarryouttheChiefengineer’ssignatureofinstructionsforconcretepouringetc.
Periodicallyortemporarilyinviterelatedspecialisttodirectonthesite.
Fulfillingandensuringmeasuresforqualitytarget
4.3.1Qualitytargetoftheworks:ensurethequalifiedratiooftheworksas100%.
4.3.2Qualityensuringsystem
Placethequalityoftheworksintheplanofcreationofgoodquality.
EstablishaqualitycontrolandgoodqualitycreationgroupsleadedbyCompany’sChiefEngineer,ManagerofEngineeringDept.,ProjectManager,ProjectEngineerandTechnicalofficer.
Obeyownerandsupervisor’sinstructionsonthesite.
WorksQualityEnsuringSystem(referencetoFigure2forthedetail):
ManagementStructureNetworkonthesite
Ensuringmeasuresforquality
Qualitycontrolofmobilization
Conducteducationofqualityconsciousnessinearnesttotheextentthatallstaffsandoperatorsfirmlyestablishthesubjectivethoughtof“QualityFirst”,andclearlyknowthequalitytargetoftheworks.
Workoutcorrespondingdetailedrulesandregulationsongoodqualitycreationplan.
Workoutensuringmeasuresforspecialquality.
Workoutqualitycontrolandqualityinspectingplansforkeyoperationsequences.
Makesureoftheresourcesoftherawmaterialsandensurethesupplyandtransportation.
Qualitycontrolintheprocess
Tellingthetechnicalandqualityrequirementsindetailpriortoexecuteanysequencestotheextentthatanyoperatorsclearlyknowtheoperationaltechnology,andthequalitypurposecanberealized.
Allconstructionsequencesmustimplementacceptancespecificationsforbuildingworksandrelatedregulationsonworks’qualitycurrentlyinforce.
Perfectlyconductconstructiondiarywork,timelydealwithconformationsheetforallalternatedworksandwellcollectandmanagethetechnicalinformationofallkinds.
Concealedworksmustbeacceptedasqualifiedinaccordancewiththeregulationsandthenextsequencecanbestartedthereafter.
Activelyconductqualitycontrolinallaspects,establishaqualityensuringsystemandadoptstandardizedworkingproceduresintheconstruction.
Asfordecorationworks,itwilladoptasampleleadedrule,cantheworksoflargeareabeconstructedonlyafterthesamplebeingconfirmed.
Activelyprompttousenewtechnologyandtechniques.
Qualitycontrolofprocurement
Preparematerialsprocurementplanasrequiredbytheproject,thematerialsprocuredshallbenotedwiththeirnames,quantities,sizes,deliverydatetothesite,deliveryways,nameofsuppliers,standardsfortestandverificationmode.
Whentheclientrequirestoverifythesuppliedmaterialsorequipment,procurementdept.mustproviderelatedcertificateofqualityandtestreport,owner’sverificationshallnotreleaseusfromtheliabilitiesforprovidingqualifiedgoodsandnoreliminateowner’srejectionofthegoods.
Controlofidentificationofproducts
Identificationsofproductsdeliveredtothesiteshallinclude:nameofdealer,manufacturer,name,quantityandsizeandtypeoftheproducts,testreport,defectsliabilitysheet,dateofproductionandcertificateofqualityetc.
Productsidentificationsshallberecordedinstoringregisterandcardafterqualifiedgoodsreceivedintostore.
Controloftestandinspection
Conductinspectionandtestwhengoodsdeliveredtothesite,inspectitsqualityassurance,qualitycertificate,testreport,asforspecialmaterials,speciallynominateapersonorpersonstoinspectthemthroughsamplingandthemethodasrequired.
Materialsnotbeinspectedandtestedshallnotbeprocessedorincorporatedintotheworks.
Processinspectionandtest
Finalinspectionandtest
Aimedmeasuresforqualitycontrol
Wewillworkoutaimedqualityensuringmeasuresindifferentconstructionsagesbasedonourgreatdealofpracticesandincorporatingwiththeactualconditions.
Qualityensuringmeasuresforrebarworks(referencetoFigure3forthedetail):
Generalmeasures
Strictlycontroltheinsertingpositionofrebarforcolumnstoavoiddisplacementofrebaranditssizenotconformtodesigndrawings.Cementgroutatthefootmustbeclearlyremovedpriortobindrebarofcolumns,andpatattentiontoitsverticalityofverticalrebar,horizontalandclipsshallnotbeboundunderinclinedconditions.Makeacontractingclipontheinsertingrebartolinkthemtogethersotoavoidanydisplacementorbent.
Rebarintheworksshallnotbealternatedwithoutauthorization,ifitsurelyneedsadjustmentbasedontheactualconditions,itmustbeapprovedbydesignerandtechnicaldepartments,andtechnicalconfirmationsheetshallbeissued.
Bentanddeformedrebarshallberectifiedpriortouseit,oilandmudonrebarshallbeclearlyremoved.
Speciallyassignapersonorpersonstomonitorwhenpourconcreteandrectifythedeviationsmayoccuratanytime.
AcceptancesheetmusthavesignatureofQualityOfficer.Qualityanalysismeetingshallbeholedinrespectoftheconstructionofeachstagetofindthedefectsandputforwardmeasuresforrectifyingthem.Assistsupervisorsinacceptanceofunitworksandcarefullyrectifythedefectssotoensurethequalityoftheworks.Startingthenextsequencecanbeconductedonlyafterthecurrentsequenceworksbeingaccepted.
Electricarcwelding
Preparationpriortothewelding.
Cleantheedgesofweldingjoints(oil,rust,dewetc.);
Inspectweldingmaterials(electrode,fluxwhetherconformtotherequirements);
Technicaldocuments(drawingsandtechnologyetc.);
Weldingequipmentetc.
Electroslaghyperbaricwelding
Beforetheformworkconstruction,configurationdesignforsupportingsystemandformworkshallbeconductedfirst,workoutthearrangingdiagram.Personinchargeofdetailingdrawingsandforemanmusttellthegrouppersonsthedetailedrequirementsinrespectofsupportingandarrangementofformwork,operationsequences,assemblingandremovingmethods.Formworkanditsfittingsdeliveredtothesiteshallbeinspectedandsortedandcountedinaccordancewiththeregulationsandquantity,allthosenotqualifiedshallnotbeused.
Axispositionandsectionaldimensionshallbecorrectlycontrolledintheinstallationoftheformwork,andthesplicedjointsshallbetight.Thejointsof1mmshallbesealedwithsuitablematerialsortinplate,ifthespanexceeds4m,anarchof0.3%shallbeformed.
Waterstoppingsteelplateofbasementshallbestrictlyexecutedinaccordancewiththedrawings,fixedwithweldingrebartoensureacorrectpositionandlevelofthewholesteelplate.
Supportingsystemofformworkmustbehorizontallyflatandverticallystraightwithfirmsupportingpoints,fastenersandboltsmustbefastened,andassembleformworkstrictlyinaccordancewiththearrangingdiagram.Speciallyassignapersonorpersonstochecktheformwork’ssupports,bolts,fastenersandcolumnclipsetc.,andrectifyittimelyifanydefectfound.
Platformsupportofformworkmustbesetupstrictlyinaccordancewithdesigndrawingstotheextentthatdownpartandupperpart,inandoutpartareuniform.
Formworkshallbeoftentrimmedandrepairedandbrushtheseparatingagent,andkeepitsleannessandflatnessifitisusedcircularly.
Strictlycarryouttherulesforconcretepouring.Relatedformalitiesfor
thetechnicaldataandacceptanceshallbegetreadypriortothesignatureofinstructionsonpouring.
Submitthemixingratioofconcretetotestcenterforthetestandforsupervisor’sreviewoneweekpriortothemixing.
Timelyknowtheweather,ifitrequirescontinuouspouringbutrains,itshallbecoveredintime,andtimelytreatthesurfaceofconcrete.
Properlygetreadyofallworkpriortothepour,equipmentshallbepriorinspectedbeforethepour,rubbishetcintheformworkshallberemoved,timberformworkshallbewateredat2nightsintervals.
Therearemanyconstructionjointsduetoarelativelargeareaoftheworks.Inordertoensurethequality,schemearrangingthejointsshallbeworkedoutpriortotheconstruction,andstrictlycarryoutit.
Rubbishetc.betweenthejointsofnewandoldconcreteshallbecheckedandremovedpriortothepour(itmayusehighpowercleaner),andwaterthembutnotaccumulatewaterthere.
Whereitisrelativelyhighanddifficultforoperation,andalargeareahavingdenseholesandrebar,clearsignsshallbesettheresotoensurethequalityofpouredconcrete.
Vibratorshallbe“Quicklyinsertedinandslowlydrawout”,toavoidconcretebeingcoursedivided,separated,aswellunnecessaryholesandairbubblesoccurred.
Duringthepourlayerbylayer,vibratorshallbeinsertedinto5cmoflowerlayerwhenvibratetheupperlayerforeliminatingjointsbetweenthe2layers,andshallbevibratedbeforetheinitialsetofthelowerlayer.Highlightthevibrationofpumpedliquidconcrete.
Elevatedpassageplateshallbelaidduringpouringforfloors,directlysteppingonconcreteshallbestrictlyprohibitedsotopreventrebarbeingdeformedordisplaced.
Properlycuretheconcrete,andtestpiecesshallbemadeatthepouringpoints.Testpiecesshallbeformworkremoved24hoursafteritformed,andcuredinstandardcoringroomtothedesignedage,thenconductstrengthtestonthem.
Inordertoensureasmoothconstructionandavoidunexpectedcircumstanceoccurred,thefollowingsshallbefocusedon”
Ensurepowerandwatersupplyonthesite;
Incaseofthepourhavingtobestopped,tensionrebarmustbeinsertedintheconstructionjoints;
Strictlycontroltheslumpofmixingtruck’sconcreteonthesitewhenpourit,andunqualifiedshallberejected.Watershallnotbefilledinthemixingtruckonthesite.
Eachpumpshallbeuniformlydirectedbyapersonspeciallyassignedtoproperlycontrolthespeedofpumptrucktoareasonablysupply.Eachpumpshallbeprovidedwith3smallvibrators.
Schemeforfabricatingconcretetestpiecesandsumptest.
Accordingtorequirementsofdifferentstrengthofconcrete,2personsforfabricatingitforseepageresistancetest,work:sampling,detailingdrawingsandcuring.
Randomlysamplingforslumptest.
Personalallocation:2groupsforfabricatingtestpieceforpressureandseepagetest,work:sampling,makingandcuring.
Sumptest:eachpersonwillberesponsibleforonepumppositionandproperlymakerecords.
Speciallyassignapersononthesideofhopperofeachpumptrucktosuperviseandremovelargestonesifany.Watershallnotbeaddedtotheconcreteonthesite,itshallbeadjustedaftertimelycontactedthebatchingplantiffoundtheslumpwasnotmeettherequirements,orrejected.
AlltestsshallbeunderwitnessbytheSupervisor.
Sincetherearemanylapsintheworks,inordertoensurethequalityoftheproducts,properprotectionoftheproductsshallbeconductedthereforeaftertheconstructionoftheconcrete.
Strictlyprohibitdrawingorwritingonconcretewall,columnormembers,andensurethesurfaceclean.
Incaseithastomakesignsontheconcretesurface,itshallbepriorconsentedbythepersoninchargeofitanddosointheindicatedposition.
Constructionmethodsandselectingofconstructionequipment
Preparationforconstruction
Fieldpreparation
Levelthesite,andlayoutwaterandpowersupply,roads,temporaryfacilitiesforproductionandlivingaccordingtoconstructionplanprovidedbyowner.
Organizeconstructionteamtopossessthesiteandconducteducationofsafetyandcivilization.
Delivertheequipmentandmaterialsontothesite.
Interiorpreparation
Befamiliartoshopdrawings,conductjointreviewofthedrawingsandtimelysolvetheproblemsbetweendesignandconstruction.
Organizetoprepareconstructionorganizationdesign,qualityassuranceplanandbudgetforeachsectionalandeachprofessionalworks.
DBJ/T13-330-2020 基于BIM岩土工程勘察技术规程(附条文说明).pdfPreparemonthlyanddailyprogressplan,prepareplansformaterials,laborsandequipmentpossessingthesite.
Inspectandtestthematerialstobeincorporatedintotheworks,andconductdesignofmixingratioasrequiredgradeofconcretestrength.
Furtheroptimizeanddetailtheconstructionmethods.
Positioningofthebuilding,measurementandsettingout
某生态绿地施工方案Positioningpoints,basepointsshallbesetfirm,notsettled,noteasilybeingdamagedandwithoutdisplacement,andshalltakeeffectiveprotectionmeasures(deepburiedandpourconcreteintoit).
Axiscontrolanditsmeasuringmethods