施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
截桩施工组织设计docOrganizationDesignofCuttingPilesWork
ConstructionScheme
ScheduleofPilingWorksofIPSProjectSYNGASPlant
GeneralSituationofProject
GB 7000.19-2005标准下载1.3ConstructionScheme
1.3.1TechnicalPreparation
Organizetechnicalpersonneltotakejointcheckupfortheworkingdrawings,tohaveknowledgeofthedesignidea,requirementandexecutiveregulationoftheproject,tomasterthequalitystandardandcontrollingmeasure.Interpretthedetailsoftechnique,qualityandsafetytotheworkingpersonnel.
Accordingtotherequest,cutofftheconcretesquarepilesandroundpilesfromnaturalground.(Naturalgroundelevationisabout14.0meters).
1.3.2PreparationofConstructionPersonnelandEquipment
1.3.2.1Personnel
Headerofcuttingteam1
Cranedrivers2
Cranedirector1
Assistantworker1
Electricwelder1
Workersofcuttingpile6
1.3.2.2Equipment
2~4tipcartsfortransportingpiles;3~4roundpilecuttingmachines;
Somesledgehammerandsteelchiselsandonecrane.
1.3.3Constructionorganizationandmethodinthesite
Methodtocuttingsquarepiles:smashtheconcretearoundtoexposereinforcingbar,andthenusegasweldingtocutthemainreinforcement.Atlast,prizethesquarepileoverwithsledgehammer,steelchiselsorchisels.Themethodoflayinglongerpilesdownwillconsulttotheroundpiles,whichwewillfastentoacraneandthenlaydown.
Methodtocuttingroundpiles:inordertoensuretheconstructionsafety,we’llfastenthepiletoacranefirstlyforthelongerpiles,andthencutitoff.Theconstructionstepsareasfollows:
Perchthecrane.
Tiethesteelropeslingonthepileandtheotherendtothehook.
Tieoneortwoassistantropestothesteelropesling.
Liftthecranehookandtwopeoplepulldowntheassistantropeatthesametimetoletthesteelropeslinginrelaxation.
Whenthesteelropeslingisliftedtoonefourthfromthetopofpile,loosentheassistantrope,andthenfixthesteelropeslingfirmly.(lookatSchematicDrawing)
Thecuttingworkshouldn’tinfluentthepilingconstruction.
Constructionschedule
Constructionschedule
Table1attached
Maintechniqueandadministrativemeasureinordertoensureconstructionperiod
Mastertheprocessofpilingworksatanymoment,collocatemanpowerinreason,andaddorminuspersonnelatanytimetoensuretheactualizationoftheplan.
Preparepersonnelandequipmentatanymomenttomakesuretheworkcanbecarriedoutassoonasrequired.
SafetyStatement
Alltheworkingrubbishshouldbecollectedindustbinandcleanedupaltogether.
Usinggasweldingmuststrictlyexecuteoperationregulationandtherequirementoftheadministratorsinthesite.Destroyingtheregulationisnotallowed.
Pushing,suspendingandloadingpilesshouldbeconductedbyspecialperson.Unsafelyworkingisnotallowed.
Whenthereinforcingbaroftheprecastpileiscutoff,thepilemustbelaydowntoavoidinjuringsomeoneincaseitfalls.
Thepileshouldbetransportedoutofthesiteintime.
扬巴一体化项目合成气装置桩基工程
《扬巴一体化项目合成气装置桩基工程进度计划》
合成气桩基工程施工目前已经进入到打桩施工阶段,受工程地质条件的影响,方桩和管桩都不能打到设计标高,为不影响施工,必须对裸露出地面的桩头截去。根据设计桩数,需要进行截桩的工作量约920余根。
a)组织技术人员对施工图纸会审,了解工程的设计意图和要求及执行的规范,掌握质量标准及控制措施,对参加施工的作业人员进行技术、质量、安全等方面的交底。
b)根据要求对混凝土方桩和管桩,截至自然地面。(自然地面高程14.0米左右)
1.3.2施工人员、设备机具准备
截桩人员不少于8人,其中作业组长负责对整个截桩工作人员进行安排调度。
1.3.2.2设备、机具
1.3.3现场施工组织和施工方法
由于施工场地的限制,为防止工作互相影响,截桩工作和打桩工作必须协调有序。按现在施工情况,截桩工作首先从控制室及变配电所开始截桩,由北向南逐步进行,然后根据打桩的施工顺序进行安排截桩工作。根据打桩工作完成情况和场地作业面的扩大进行调整。
方桩的截断,先将桩四周混凝土砸掉露出钢筋,然后用气焊割断主筋,最后用大锤钢钎或凿子将方桩撬倒。对于较长的桩在放倒时参照管桩用吊车稳固后放倒的方法。
管桩的截断,为了保证施工安全,在将比较长的桩进行截断时,采用吊车稳固管桩后再进行截断。施工步骤如下:
在管桩上系钢丝绳套,挂在吊车吊钩上;
在钢丝绳套上系好一至两根钢丝绳套辅助绳;
提升吊车吊钩,在提升吊钩时两人同步将绳套辅助绳向下拉,使钢丝绳套处于松弛状态。
当钢丝绳套提升至距桩顶1/4处时松开辅助绳,将钢丝绳套吊紧固;(见示意图)
拆卸无齿锯,人员和设备移至安全地带;
指挥吊车转动吊臂,将管桩放倒。
桩头截断后集中车辆和人力装车外运。
截桩工作不能影响打桩施工作业。
2.2保证工期的主要技术、管理措施
2.2.1随时掌握打桩进展情况,合理配置劳动力,随时增减人员,确保计划实施。
2.2.2机具,人员随时作好准备,作到随叫随到。
3.1参加截桩施工人员必须是经过IMT的培训,取得证件后方可进场施工。
3.2截桩施工人员必须遵守施工现场的一切规章制度。
3.3截桩施工人员必须佩带安全帽、劳保鞋、防护镜。
3.4截桩时注意过往行人,防止砼碎块飞溅伤人。
3.6动用气割工具,必须严格执行其操作规程及现场安全管理人员的要求。不得违章操作。
3.7经常检查索具,保证索具的安全性。
3.8推桩、吊装必须有专人指挥。不得野蛮施工。
3.9预制桩钢筋被截断后必须将桩放倒,防止倒塌伤人。
3.10桩推倒后应及时运出现场
扬巴一体化项目合成气装置桩基工程
CONSTRUCTIONAREA
PILEQUANTITY
重庆市建设工程施工机械台班定额(2018年版) 控制室CONTROLBUILDING&SWITCHROOM
蒸汽转化炉REFORMER
原料预处理工段REACTOR
储罐区MDEASTORAGE
DB45/T 2125-2020标准下载CO2脱除工段CO2REMOVAL
压缩机COMPRESSOR