施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
建筑施工卸料平台施工方案一、设计概况·································2
二、设计依据·································2
三、次梁设计·································2
浙江省城市桥梁隧道运行安全风险防控导则(试行)(浙江省住房与城乡建设厅2020年1月)四、主梁设计·································4
五、铺板设计·································5
六、钢丝绳验算·······························6
七、吊环设计·································7
八、钢平台安装·······························7
九、附制安图·································8
钢平台设计尺寸长3m、宽2m,主梁用工字钢、次梁用槽钢制作,上铺50mm厚木板,用钢丝绳斜拉固定在剪力墙或梁上。允许荷载:施工荷载1.5KN、集中荷载5KN.
次梁选用槽钢14制作,3m长钢平台设4道次梁,次梁槽钢焊接在主梁凹槽内(主梁侧加100×60×8垫板),其间距为1m。14槽钢截面特性为重量0.1KN/m,WX=39.7cm3,h=100mm,t=8.5mm
铺木板=0.4KN/m2
施工均布活荷载=1.5KN/m2
永久荷载分项系数=1.2
可变荷载分项系数=1.4
木跳板50mm厚=0.4×1×1.2=0.48KN/m
14槽钢=0.1×1.2=0.12KN/m
施工均布荷载P=5×1.4=7KN
M=(1/8)ql2+(1/4)P1=(1/8)×2.7×22+(1/4)×7×2=4.85KN·m
M/(VX×WX)≤f,VX=1.2
δ=(4.85×106)/(1.05×39.7×103)=116N/mm2<f=215N/mm2满足要求;
MX/(Ab×Wx)≤f,ψb={570tb×/(1×h)}×(235/235)=1.16
Ab={(570×8.5×48)/(2000×100)}×(235/235)
M/(Ab,×WX)=(4.85×106)/(0.777×3.97×103)157N/mm2<f=215N/mm2
主梁选用工字钢16制作,其截面特性为重量0.123KN/m,
Wx=61.7×103,h=16mm,b=53mm,t=9mm
主梁均布荷载:Σ1260.123×1.2=0.148KN/m
栏杆、密目安全网:0.115×1.2=0.138KN/m
300×300mm木挡板:0.072×1.2=0.068KN/m
Σq=0.37KN/m
P1=(1/2)×{(0.48+2.1)/2}×2+(1/2)×0.12×2=1.41KN
P2=(1/2)×2.7×2=2.7KN
M=(1/8)×0.37×32+2.7×1+(1/4)×7×3=8.37KN·m
RA=RB=(1/2)×0.37v3+1.41+2.7=4.7KN
MX(VX×MX)=(83.7×106)/(1.05×61.7×103)=129N/mm2<f=215N/mm2,满足要求;
MX/(Ab×Wx)=(8.37×106)/(0.925×61.7×103)=147N<f=215N/mm2
ψb=(570×9×53)/(1000×126)×(235/235)=2.16
选用3m长50mm厚松木板,板宽不小于250mm,板端头用螺栓与槽钢相固定。
Q=(0.4×1×1.2)+(1.5×1×1.4)=2.58KN/m
P=5×1.4=7KN
M=(1/8)ql2+(1/4)P1=(1/8)×2.58×12+(1/4)×7×1=2.07KN·m
δm=M/Wn≤fm=17N/mm2
W=(1/6)bh2=(1/6)×100×52=417cm3
δm=(2.07×106)/(4.17×105)=5N/mm2≤fm=17N/mm2,满足要求;
T=P1sina=4.7/0.707=6.65KN
用¢14mm、公称抗拉强度1550N/mm2的6×19钢丝绳作捆扎吊索,查表得钢丝绳的钢丝破坏断拉力总和为Fg=112.0KN。
查表得钢丝绳的安全系数K=6,钢丝绳的换算系数a=0.85。
〖F〗=(a×Fg)/T=(0.85×112)/6.65=14.3KN>〖K〗=6,满足要求。
在钢平台主梁上设吊环,位置详见安装图,吊环用210×100×8的钢板吊在主梁端部,钢板上割¢40圆孔,利用圆孔作吊环。为防止钢板锐角切割钢丝绳,在圆孔处钢板二面各焊¢14钢筋,与切割圆孔平,详见节点图A。
δ=(6.65×103)/480=13.9N/mm2<f=215N/mm2,满足要求。
1、安装时用塔吊就位JJG 377-2019标准下载,将钢平台一端放在梁上部且搁置长度不小于30cm,主梁两边用预埋吊环固定在梁上,然后将钢丝绳上部绑扎在上部预埋件内,用花篮螺栓调整两端平整度达到规范要求。
2、安装时钢丝绳卡每段不少于4个,上夹头时一定要将螺栓拧紧,直到绳被压扁(1/3)~(1/4)直径为止,并在绳受力后,再将螺栓拧紧一次,以保持节头牢固。
3、安装时操作工人必须系好安全带,待安装完毕后,塔吊方能松下吊钩。
T/CHTS 10023-2020 公路桥梁钢箱梁、钢桁架和钢塔制造与安装技术指南.pdf4、钢平台安装后必须由现场专职安全员检查并按设计荷载试验合格后方能正式投入使用。
5、使用中应每天上、下班前设专人检查,发现问题及时处理,严禁施工荷载超过设计允许荷载。
XX地质家园XX项目部